Long time readers of this blog know (we hope) that we have always tried very hard not to dwell on our personal situation, even though we do occasionally report on what’s happening around our property. But when we do, we generally do it to illustrate more general principles about the way Enbridge often carelessly and thoughtlessly (or callously) conducts its business. So it is with the story we have to tell today.
First, just a little context. In the temporary workspace that Enbridge required on our property was a stand of over 100 trees (some of them were also within Enbridge’s existing easement) and our precious perennial garden, which we planned, dug, planted, and tended ourselves over a period of years. This is what it looked like the spring before Enbridge arrived:
Enbridge leveled all of it. And because there was nothing we could to to prevent them from doing so, we instead gave a great deal of thought and concern to restoration. We’re obviously not a farm, but in order to replant some version of our green wall and our garden, we need productive, fertile soil. From the start, this has always been our primary concern.
Our attempts to have some assurances about care and handling and restoration of our soil inserted into our agreement with Enbridge during negotiations were summarily rejected. Instead, they just referred us to their general remediation practices (we could show you the emails from our ROW agent) and said, essentially, “trust us.” They directed us to the “Environmental Impact Report” on file with the Michigan Public Service Commission for a description of those practices. So let’s take a quick look at a bit of that document.
Under “Clearing and Site Preparation” the report says that “All brush and other materials cleared from upland areas within the construction corridor will be placed as a windrow along the construction corridor and disposed of as agreed to with the landowner.” In our case, what Enbridge agreed to is this (from our construction line list): “Trees with with pink ribbons are to be cut and saved for landowner at NE corner of property. Trees without ribbons are to be cut and hauled away.”
Here is what that looked like after construction crews did their clearing:
Two things to note here. First, that pile of timber on the left side of the image? Those are the trees we asked to have saved. But that’s not, as the agreement states, the NE corner of the property. And second, see the piles all along the orange fence in the middle and right of the image? That’s the shredded remains of the rest of the trees. Those piles should have been hauled away– that’s what we wanted to happen; that’s what we were told would happen– according to our agreement. But as you can see, they weren’t. In fact, they’re still there now (as you’ll see in a moment).
Now, we never complained about either of these things. The timber placement isn’t really a big deal and while we feared the shredded material might eventually become a problem, we trusted that they’d keep it segregated and haul it away after the pipe is placed in the ground. And since we don’t really like to complain constantly, we let these things go.
Much more important than those matters is what the Enbridge Environmental Impact Report and our agreement have to say about the handling of soil (much of which, in our case, isn’t ordinarily topsoil as we brought in loads of rich garden soil when we created our perennial bed). And we’ll just reiterate that we invested a lot of love and sweat into that soil, which is why, as some of you may recall, we were so upset the day a bulldozer started pushing the neighbor’s weed-filled dirt onto our property.
Anyway, here’s what it says in the Impact Report:
Topsoil generally has physical and chemical properties that are conducive to good plant growth. To prevent the mixing of topsoil with less productive subsoil during construction, topsoil will be segregated in selected areas where soil productivity is an important consideration. A minimum one foot of separation must be maintained between the topsoil and subsoil piles to prevent mixing. Where the one foot separation cannot be maintained, a physical barrier, such as a thick layer of straw mulch, may be used between the spoil and topsoil piles to prevent mixing. Use of the physical barrier must be reviewed and approved by Enbridge on a site-specific basis.
So far more than the handling of cleared timber, we’ve always been concerned about this practice, especially the segregation of subsoil and topsoil. That’s why we had this listed also, very clearly, in our line list agreement, which says: “Separate topsoil from subsoil, upon completion restore topsoil to surface and properly de-compact the work area.”
It’s hard to see the pile of stripped topsoil in the picture above, but it’s on the far side of the piles of shredded material. Here are a couple of up-close pictures, the second from a different angle, of the pile of topsoil (in the foreground):
And here is just one more, looking along the temporary workspace line. Behind the orange fence, you can see the shredded material and the pile of topsoil to the left of that. Now, we can tell you that plenty of excavated subsoil was placed in close proximity to this topsoil, certainly closer than the one foot separation listed in the Report.
So where is this headed? Well, yesterday construction crews were hard at work on our property, finally putting the pipe in the ground. That means some serious excavation– the removal of lots and lots of subsoil. And in one place, where they will tie in to the pipe they bored underground several weeks ago, they had to install a big blue steel box because the slope of the trench walls are very steep. Here’s a look:
By now, we’re sure you know where this is going. All of that dirt (clay, really) they excavated to lay the pipe and install that big blue box had to be piled somewhere. Here they are piling it:
See where they put all that excavated subsoil? Yep, right on top of our topsoil and even spilling into and onto the shredded material. So much for segregation. Here is a shot from the same angle as the one of the topsoil above:
And here is a closeup of the new mixture:
As we said at the start of this post, we don’t like to dwell on our personal situation. Mostly that’s because we know very well that compared to many others affected by this project– like our friends Beth Duman and Amy Nash, not to mention plenty of other people we’ve heard from or heard about– we don’t have it so bad, even though the state of soil on our property does mean a great deal to us. Many good people along Line 6B are in far, far worse situations than we are. We are very sensitive to that fact.
But that doesn’t excuse these violations. In fact, the sort of thing we’re describing here has happened and is happening all up and down the line. Enbridge would have you believe that these are just mistakes, aberrations. That’s what we’ve been told in the past by Enbridge executives. Mark Sitek told us, “we’re not perfect.” Mark Curwin told us “mistakes happen.” And those things are probably true. We get that. We even let little mistakes (like the placement of those felled trees) pass.
But when these things happen repeatedly (we’ve documented how many just on our property?). when a large percentage (a third? half?) of landowners have each witnessed two, three, four, or more “mistakes” on their own properties, when the same sort of “mistake” is made over and over again, well, then it ceases to be a mistake and has to be called a pattern of behavior, evidence of shoddy practices. And it’s a pattern of behavior and a set of practices that are totally at odds with the way Enbridge presents itself to the public and with the way that Enbridge presented itself to the MPSC. In fact, as our citations from the Environmental Impact Report (submitted as evidence to the MPSC) show, Enbridge, one can only conclude, simply misrepresented to that agency the way that it conduct its business. (Not that the MPSC much cares.)
Now, we’re not without some slight measure of confidence– though we’re extremely wary– that Enbridge will try to take steps to make this situation with our soil right. But it’s going to take a fair amount of effort and convincing on our part, adding more frustrating experiences to our already rich store of them. And the fact is, as we have said dozens of times, it didn’t have to be this way. It doesn’t have to be this way. If only they just do as they say.
If only they would do as they say….
I know your frustration. We too had a love for our land, trees and our gardens.like you we put our hearts and much hard work into our landscape an flower beds.
It’s hard, we try not to complain either.
Our experience with the soil separation the same.
However what they claimed to separate today was mixed with all the material on site…
Asphalt, drain tile, tiles, plywood, gravel… You name it. Also there was no measures taken to separate broken asphalt when back filling the pipeline trench.
With great thanks to the pipeline safety trust we have discovered a regulation that requires an additional 12″ of soil coverage when within 50′ of a residence (a depth of 48″ from the top of the pipe) However by measurements it looks as though the pipeline was not placed with a consistent depth of 48″ as required.
We pray PHMSA will protect us and back the only set regulation in place to ensure our safety.
Many blessings to all the landowners.
Our hearts go out to you each.