Bits of information on the proposed ET Rover project have been trickling in, none of it verified with any absolute certainty. Here is what we have learned (or heard) since our last post:
- If you’re on Line 6B and you’re like us, it crossed your mind that this project might re-use the now-abandoned old Line 6B that is sitting idle in your back (or front yard). We never really thought that was very likely, but the fact that Enbridge has recently partnered with Energy Transfer to convert a gas line to crude made us a little nervous. So we wanted to Enbridge to go on record on this matter. Yesterday, Jason Manshum verified that “there are no plans to use the original Line 6B for this other project.” We’d have preferred that he put that a bit more directly, but it appears that we can (more or less) rule out the possibility of recommissioning the old Line 6B. That’s good news.
Unfortunately, Energy Transfer has not returned our two phone calls (no idea why), so the other information we have to share is coming from other landowners. Here’s what we’ve been told:
- The ET Rover route will NOT use the Line 6B corridor or easements, although it will loosely parallel the route, running north of Line 6B (how far north, we can’t say). Energy Transfer will be seeking NEW 60 foot easements from landowners and, presumably, municipalities. That’s not such good news. The image above shows a portion of the route running through a portion of Howell– and right through a subdivision! Line 6B is several hundred feet to the south of the blue ET Rover line in the image.
- According to the ET representative in one of our readers’ phone calls, the letter was sent to anyone in a 500 ft. radius of the line. If the proposed line runs through your property, it appears you would have received an additional letter and perhaps (even likely) a phone call asking for permission to survey your land. It is our understanding that many landowners are refusing that request. Please note that you DO NOT have to allow them to access your property to survey. You can just say no.
- This is the very beginning of a long process (please refer to the resources at the Pipeline Safety Trust website describing the FERC approval process). Energy Transfer has not yet fulfilled the requirements to file a permit application with FERC. The process can take a couple of years to run its course. That said, it’s best to inform yourself, make your wishes known, and organize with your neighbors and your local officials early.
- A reminder that the first of the ET Rover open houses is July 14 in Fenton. It is likely that company officials and/or land agents will conduct the open house informally, preferring to speak to landowners individually rather than collectively. This is NOT to your advantage. We strongly recommend that landowners gather together to make the open house a group affair. That way, everyone can hear everyone’s concerns and continuity of information will be assured. For reference, here is part of an account of how shrewd landowners in Wisconsin prevented Enbridge from controlling information in a similar fashion:
It was a combative format Enbridge was attempting to avoid when it originally organized the meeting to be an open-house format, with residents asking questions one-on-one with Enbridge representatives. However, some of the more than 75 attendees, including many political candidates who empathized with the crowd, were unhappy with the format and quickly began setting up chairs for a group presentation, succeeding in turning the session into two-hour group question-and-answer session. The group, closely monitored by two Jefferson police officers, then proceeded to drill the company representatives on everything from the company’s safety procedures to the pipeline welds, the content of the material flowing through the pipelines and their environmental record.
Lastly, if you are as concerned as we are not just about your own property and the treatment of your neighbors, but about pipeline safety in general, please take a moment to share (or even adapt) the open letter we wrote to Attorney General Schuette and DEQ Director Wyant regarding the newly proposed Michigan pipeline safety task force. The fact that the assembled task force does not include any landowners, property rights advocates, or conservationists is unconscionable. The only way to ensure that landowners do not continue to suffer at the hands of these energy expansion projects is to give them a prominent voice in the process. Regular citizens need to put pressure on their elected officials, at all levels, to make this happen. We’ll try to post more updates to our Facebook page as we receive them. Please stop by and give us a “like.”
Thank you so much for this information. I have been astounded by the secrecy of this pipeline. I called my township, my county, DEQ, and no one knew anything about this. I talked with the attorney general’s office and got zero information. I am so frustrated with the lack of information surrounding this project. It seems like a deliberate attempt to keep as few people informed as possible so that there won’t be any public push back. Just can’t believe this!
Ruth
Yet another reason we need ordinary citizens on that task force. Our officials simply aren’t paying attention!
Jeff –
How were you able to get the map???
Hi Beth-
Donna Taylor got the map from someone at ET. I’ve written to the same person asking for more.
I have received both letters as of last week. I am refusing them to do a survey. I am still waiting for Enbridge to restore my property. This is unbelievable to say the least.
Some towns in Colorado are declaring themselves frack free zones. I’d like to suggest that townships in Michigan band together to name ourselves pipeline construction free zones, frack-pipeline free zones, and new pipeline free zones. Otherwise, it’s just going to keep happening over and over again. We can do it; all we need to do is organize.
A new 60 foot easement is VERY bad news!