We don’t know about others along the pipeline, but we are receiving periodic construction updates from our ROW agent (we’re grateful for these). Here is the latest:

Clearing crews have finished work on land east of US 23 to Taylor Road. Pipe has been dropped off on property for a few miles east of 23. No welding has begun.

Survey crews, ahead of the clearing crews, are making their way east a few miles in advance and will apparently be picking up the pace. Surveyors could be in Groveland Township as early as next week, as they were on Milford Road today. According to best estimates, the clearing crew will be at Milford Road by the end of this week.

We will continue to update everybody on any updates we receive.